Align scope and period before calling a result an overrun. Separate quantity, unit-price and omitted-item differences, then investigate evidence before reducing service quality.
Actual spending can exceed a plan because more units were bought, prices changed or delivery was never budgeted. A single total difference does not tell the responsible person what to fix.
Make the comparison consistent
Check matching items, periods, units and clearly explained tax or currency bases. Comparing a purchase order with cash paid may introduce timing differences that should be separated first.
When scope changes, retain the original plan and record the amendment. Rewriting history to equal actual spending hides the decisions made along the way.
Explain the difference
| Item | Information needed |
|---|---|
| Plan | Quantity, unit price and inclusions |
| Actual | Evidenced quantity and price |
| Quantity change | Why more or fewer units were bought or used |
| Price change | Supporting supplier documentation |
| Added item | Charge absent from the original plan |
| One-off or recurring | An evidenced explanation |
| Follow-up | Owner, missing evidence and required decision |
A worked hypothetical example
Suppose a purchase was planned at 100 units costing 20 baht each: 2,000 baht. Actual purchase was 120 units at 22 baht: 2,640 baht. The difference is 640 baht.
Using planned price for the quantity component gives (120−100) × 20 = 400 baht. Using actual quantity for the price component gives 120 × (22−20) = 240 baht. Together they reconcile to 640 baht. State and consistently apply the chosen method to avoid double counting.
If delivery is an additional charge, show it separately before arriving at the total variance. These fictional figures explain the method; they are neither recommended prices nor Kines operating data.
Higher quantity is not automatically waste
Examine whether activity increased, supplies were stocked or an error occurred. Buying during a month does not establish consumption during that month. Do not remove necessary items merely because quantity exceeded budget. Equally, investigate product scope and terms before judging a higher price.
Unsupported amounts remain unexplained differences. Do not spread them across categories just to make a report look complete.
Turn the analysis into one assigned action
An action might request a usage breakdown, verify supplier terms or add an omitted item to the next plan. Assign responsibility and retain closure evidence. Connect the finding to the monthly owner report, separating established facts from pending explanations.
Frequently asked questions
Must every difference be split into price and quantity?
No. The data may not support it, or scope may differ. Explain what can be established and retain the unknown portion. A complete arithmetic split does not guarantee a correct causal explanation.
Is spending below budget always good?
No. Work may be incomplete or an invoice may not have arrived. Check delivery and timing as well.
Make reporting support decisions
Discuss management and reporting scope through LINE OA @kines, using examples without sensitive information.
Tool provenance
This Kines worksheet adapts KB cost and improvement themes. Its arithmetic is a hypothetical variance illustration, not an achieved cost-saving result.